| Press Capacity |
Rated forming force and working pressure |
Select a rated force that exceeds the calculated forming load, with an engineering margin commonly considered during die and material evaluation. Confirm that the hydraulic system operates within the designed pressure range. |
Review force calculations, material specifications, pressure diagrams, and factory acceptance test results. |
High |
| Production Output |
Cycle time, loading time, unloading time, and changeover time |
Define the required parts per hour before selecting the line. Include dwell time, slide return time, material handling, inspection, and planned changeovers in the calculation. |
Run a timed production trial using the actual material, die, lubrication method, and handling process. |
High |
| Guarding and Access Control |
Fixed guards, interlocked doors, perimeter fencing, and controlled access points |
All hazardous press and transfer areas should be protected against unintended access. Interlocks should prevent the hazardous cycle from starting when a protected access point is open. |
Inspect the safeguarding layout and test every interlock, guard switch, and access gate under operating conditions. |
High |
| Presence-Sensing Protection |
Light curtains, laser scanners, or other presence-sensing devices |
Use devices suitable for the press hazard and installed at a distance that accounts for stopping time. The safety function should stop or prevent hazardous motion when the sensing field is interrupted. |
Check the safety distance calculation and perform a validated interruption and restart test. |
High |
| Emergency Stop System |
Emergency-stop buttons and accessible reset controls |
Emergency stops should be clearly identified, easy to reach, and positioned near operator, setup, inspection, and maintenance locations. Resetting an emergency stop should not automatically restart the press. |
Test each emergency-stop device during commissioning and confirm controlled stopping, fault indication, and manual reset behavior. |
High |
| Safety Circuit Reliability |
Safety relays, safety PLC, redundant valves, and monitored hydraulic functions |
Safety-related control functions should be designed according to the required risk level and validated for the complete line, including conveyors, robots, transfer units, and the press. |
Request the risk assessment, safety circuit diagrams, validation records, and proof-test procedures. |
High |
| Hydraulic System Quality |
Pump, valve, cylinder, accumulator, filtration, and leakage control |
The hydraulic circuit should maintain stable pressure and repeatable slide movement without excessive leakage, vibration, or temperature rise. Filtration should match the hydraulic components and operating conditions. |
Measure pressure stability, oil temperature, leakage, noise, and slide-position repeatability during a sustained production test. |
High |
| Dimensional Quality |
Part thickness, height, flatness, hole position, and forming angle |
Define tolerances from the approved part drawing. Confirm that the press, die, sensors, and process controls can repeatedly maintain the required tolerances throughout the production run. |
Use calibrated gauges or a coordinate measuring system to inspect first-off parts and samples from the beginning, middle, and end of the run. |
High |
| Process Monitoring |
Force, pressure, stroke position, speed, temperature, and cycle alarms |
Monitor the process variables that directly affect part quality. Configure upper and lower limits, alarm messages, data recording, and controlled rejection of nonconforming parts. |
Review the HMI screens, alarm history, trend data, recipe controls, and traceability records. |
High |
| Material and Part Traceability |
Lot identification, recipe control, inspection records, and rejected-part handling |
Each production batch should be traceable to its material lot, tooling setup, process recipe, operator or shift, and inspection results. Rejected parts should be physically separated or electronically locked out. |
Perform a traceability exercise from a finished part back to the material and process records. |
Medium |
| Tooling Changeover |
Die installation, alignment, clamping, storage, and changeover access |
Provide positive die-location features, secure clamping, lifting provisions, and clear access for setup. Changeover steps should be documented and possible without entering an unprotected hazardous area. |
Measure a complete changeover using the intended lifting equipment and trained setup personnel. |
High |
| Maintenance Access |
Access to filters, valves, cylinders, sensors, electrical panels, and lubrication points |
Routine service points should be reachable without removing unnecessary machine structures. Provide safe platforms, doors, isolation points, lighting, and space for tools and component removal. |
Conduct a maintenance walk-through and record the time required for filter replacement, sensor access, lubrication, and inspection tasks. |
High |
| Energy Isolation |
Lockout and isolation of hydraulic, electrical, pneumatic, mechanical, and stored energy |
The line should include clearly identified isolation devices and procedures for releasing residual hydraulic pressure and other stored energy before maintenance begins. |
Verify isolation points, pressure-release functions, lockout labels, and the written energy-control procedure. |
High |
| Preventive Maintenance |
Service intervals, spare parts, lubrication, oil care, and inspection tasks |
Provide a maintenance schedule based on operating hours, cycles, oil condition, filter condition, wear, and safety-device tests. Critical spare parts should be identified before production starts. |
Review the maintenance manual, recommended spare-parts list, lubrication chart, and sample service records. |
Medium |
| Controls and Integration |
PLC, HMI, recipe management, conveyors, robots, sensors, and communication interfaces |
The complete line should have coordinated start, stop, fault, reset, and safe-state logic. Product recipes should be access-controlled to prevent unauthorized parameter changes. |
Test automatic, manual, setup, fault-recovery, and communication-loss modes with all connected equipment. |
High |
| Noise and Working Environment |
Noise, hydraulic heat, oil mist, lighting, and operator ergonomics |
Evaluate noise and heat under normal production conditions. Provide suitable lighting, clear sight lines, ergonomic loading height, and controls that minimize repetitive strain. |
Measure workplace conditions during a representative production cycle and compare them with applicable local occupational requirements. |
Medium |
| Documentation and Training |
Risk assessment, drawings, manuals, software backups, and operator training |
Supply current electrical and hydraulic diagrams, safety documentation, operating instructions, maintenance procedures, troubleshooting information, and controller backups. |
Use a documentation checklist and verify that operators and maintenance personnel can complete required tasks safely. |
High |
| Acceptance Testing |
Factory acceptance test and site acceptance test |
Define measurable acceptance criteria for safety functions, cycle time, force, pressure stability, dimensional capability, alarm response, and maintenance access before purchase. |
Sign an agreed test protocol using the intended material, tooling, production recipe, and sampling plan. |
High |